Friday, July 24, 2009

Sewer construction update

I drove through there today and they have pretty much gotten all the big equipment out of the area and have filled the big holes on 13th. They should have it pretty much finished by early next week.
d
Email from Alderwood Water District.

North Creek North Segment Construction Update: (208th Street SE to 196th Street SE Snohomish County)

FCCC will continue removing shoring and begin restoration of shafts along the south side of 208th Street SE.

FCCC and KLB Construction will continue with general cleanup and roadway restoration along 13th Drive SE.

FCCC and KLB construction crews will continue to work a standard 10 hour shift Monday thru Thursday. Friday’s will be reserved for low impact work and will only as necessary.

North Creek South Segment Construction Update: (228th Street SE to 208th Street SE City of Bothell)

FCCC will continue removing shaft shoring and restoration located at the Arden Property.

Asphalt paving for the Arden Property is scheduled for the week of August 10th.

KLB will continue with general site cleanup. Asphalt paving and curb replacement have been completed for the New Tower property. Landscape restoration will be completed within the next few weeks.

General Information

For questions regarding road improvements in Snohomish County please contact Doug McCormick, Snohomish County Program Planning Supervisor at 425-388-6655 or dmccormick@snoco.org.

If your neighbors would like to be added to the email distribution list, please have them contact the email box NorthCreek@awwd.com and we will get them on our email distribution list. If you have any issues, please contact Jay Hueter of Jacobs Engineering at 425-241-1023 or at jay.hueter@jacobs.com. In addition, the District’s Construction Project Manager, Bob Hastings is available to answer your questions or meet with you as needed. Bob can be reached at 425-743-4605 or bhastings@awwd.com.


Bob Hastings
Construction Project Manager
Alderwood Water and Wastewater District
bhastings@awwd.com
Tel. 425-743-4605
Fax 425-742-4562

Tuesday, July 21, 2009

Featured New Listing















This excellent three bedroom 2 ¼ bath tri-level at 19602 9th Dr. SE in Bothell is in move-in condition on a huge 10,000 sq ft corner lot with a fenced back yard. There is a built-in surround-sound system in the family room and you can enjoy your own apples, blueberries and grapes on the party sized deck that has just been refinished. In the master suite there is a double shower in the 4-piece bath and a walk-in closet. This wonderful home is close to shopping at Thrashers Corner and Alderwood Mall with I-405 and I-5 just minutes away. It is in the highly rated Northshore School district with the school bus stop right across the street. Hardwood and laminate on the main level, brand new carpet in the upstairs bedrooms and lower level family room. All this for just $360,000.

If you have any questions or would like to see this or any other home in the area for yourself, please give me a call 206-214-5408 or email dennisgould@kw.com.

Wednesday, July 15, 2009

Another Sewer construction update!

Here is the latest from the Alderwood Water District on the sewer construction mess on 14th and 13th just north of 208th. It sounds like they will finally be finished patching it up on the 24th of July THIS YEAR! woopie!!
d

North Creek Construction Update for the Week of July 20, 2009‏
From:
Bob Hastings (BHastings@awwd.com)
Sent:
Wed 7/15/09 3:42 PM
To:

Frank Coluccio Construction (FCCC) will be completing installation of the last open trench manhole. Removal of the shoring and backfilling of the shaft will be part of the manhole installation. This work is scheduled to be completed by Friday July 24th.

FCCC will be removing shoring and begin restoration of shafts along the south side of 208th Street SE.

FCCC and KLB Construction will continue with general cleanup and roadway restoration along 13th Drive SE.

FCCC construction crews will continue to work a standard 10 hour shift Monday thru Thursday. Friday’s will be reserved for low impact work and will only as necessary.

KLB construction crews are scheduled to work a standard 10 hour shift Monday thru Thursday. Friday and Saturday work is not currently scheduled (or expected) for this crew.

North Creek South Segment Construction Update: (228th Street SE to 208th Street SE City of Bothell)

FCCC will continue removing shaft shoring located at the Arden Property.

KLB will continue with general site cleanup. Asphalt paving for the New Tower property will be followed by curb replacement and landscape restoration.

Asphalt paving for the Arden Property is scheduled for the week of August 10th.

General Information

For questions regarding road improvements in Snohomish County please contact Doug McCormick, Snohomish County Program Planning Supervisor at 425-388-6655 or dmccormick@snoco.org.

If your neighbors would like to be added to the email distribution list, please have them contact the email box NorthCreek@awwd.com and we will get them on our email distribution list. If you have any issues, please contact Jay Hueter of Jacobs Engineering at 425-241-1023 or at jay.hueter@jacobs.com. In addition, the District’s Construction Project Manager, Bob Hastings is available to answer your questions or meet with you as needed. Bob can be reached at 425-743-4605 or bhastings@awwd.com.


Bob Hastings
Construction Project Manager
Alderwood Water and Wastewater District
bhastings@awwd.com
Tel. 425-743-4605
Fax 425-742-4562

Monday, July 13, 2009

13th Ave SE Sewer Construction Update

This is the latest from the Alderwood Water District about the on-going construction project in the Thrasher's Corner area.
d

North Creek North Segment Construction Update: (208th Street SE to 196th Street SE Snohomish County)

Frank Coluccio Construction (FCCC) will continue backfilling and restoring the micro-tunneling shafts located along 13th Drive SE.

FCCC construction crews will continue to work a standard 10 hour shift Monday thru Thursday. Friday’s will be reserved for low impact work and will only as necessary.

KLB construction crews are scheduled to work a standard 10 hour shift Monday thru Thursday. Friday and Saturday work is not currently scheduled (or expected) for this crew.

Last week a section of the existing sewer had to be removed and bypassed to get the shoring in, install the new pipe and remove the shoring. In the process of removing the shoring and restoring the existing pipe the side walls began caving. The contractor was slowed significantly due to the soils and safety issues. This unforeseen circumstance required extended hours for the contractor to safely control the excavation and secure the site.

Similar issues have occurred in the past along this portion of the project due to soil conditions, safety issues and other difficulties with the deep excavations and complexities associated with a very complex project.

These occurrences are very unfortunate and the District has appreciated your patience and understanding.
The District apologizes for the inconveniences and disruption to your daily routines.

KLB will be completing the installation of the last portion of open trench along 13th Drive SE. Open trench pipe installation is scheduled to be completed this week. Thank you again for your patience! The pipe installation will be followed by trench pavement repair and cleanup.

KLB has completed the open trench pipe work along 196th Street SE east of SR-527 (Bothell-Everett Highway). This final asphalt pavement overlay is scheduled for this week.

General cleanup by both FCCC and KLB will be ongoing.

North Creek South Segment Construction Update: (228th Street SE to 208th Street SE City of Bothell)

FCCC will continue removing shaft shoring located at the Arden Property.

KLB will continue with general site cleanup and preparation for asphalt paving. Asphalt paving for the New Tower property is tentatively scheduled to happen this week followed by curbs and completion of the landscape restoration .

Asphalt paving for the Arden Property is yet to be scheduled.

General Information

For questions regarding road improvements in Snohomish County please contact Doug McCormick, Snohomish County Program Planning Supervisor at 425-388-6655 or dmccormick@snoco.org.

If your neighbors would like to be added to the email distribution list, please have them contact the email box NorthCreek@awwd.com and we will get them on our email distribution list. If you have any issues, please contact Jay Hueter of Jacobs Engineering at 425-241-1023 or at jay.hueter@jacobs.com. In addition, the District’s Construction Project Manager, Bob Hastings is available to answer your questions or meet with you as needed. Bob can be reached at 425-743-4605 or bhastings@awwd.com.


Bob Hastings
Construction Project Manager
Alderwood Water and Wastewater District
bhastings@awwd.com
Tel. 425-743-4605
Fax 425-742-4562

Sunday, July 12, 2009

Real Estate News and Resources

Well, here comes the sales pitch. You knew this blog would not be just for entertainment purposes for ever didn't you?
If you are looking to buy or sell a home in the Thrashers Corner, Bothell or Mill Creek areas check out this link to my Keller Williams web site. On the first page is a FREE search box for finding homes that are available just about anywhere in the Puget Sound region. You do not need to put in your contact information to utilize the search site. Once you put in your basic search request, you will get to a screen that allows you to choose 'map search' from the menu. This is by far the best way to see what homes are available in any neighborhood you would like. The search can be narrowed down by price, features, lot size or age of home. Just be sure to call me when you would like to view homes in the Bothell and Mill Creek areas or to find out what price range of home you are qualified for. At Keller Williams Realty Everett, we have a Metrocities Mortgage rep right in our office or you can use any lender you choose to get pre-approved and know exactly what price range you can afford.

There is also another contact button on the first page of my website for people who would like a Market Analysis of their home. It is FREE as well and there is no obligation. Just send in your contact info or give me a call and i will check out other comparable homes in your area that have sold recently and let you know what yours could sell for.

All you need to do is click here to get to my KW website to start your search.
Thanks.
d

Saturday, July 11, 2009

Centennial Park




The new Centennial Park in Bothell is a great new addition to the Thrashers Corner area. It is still a work in progress as the 1906 school house (shown in the background in this photo) is still being put in place on its new foundation. Construction is expected to be completed by the end of July 2009 and the building will be lowered onto the new foundation which is being built right now. A cement wheelchair ramp leading up to the front door should also be completed by the end of the month. The building has never had a foundation before as it was just sitting on the dirt when it was picked up and moved to its new home. Several of the support beams had to be replaced as over 100 years of contact with the dirt caused quite a bit of rot.Once the building is set in place the remainder of the refurbishing job has to be put on hold as money for the project has dried up. This building was the first school in Bothell and it will make a great addition to Centennial Park once it is completely restored. Expect updates on this project as they become available.
d

Wednesday, July 8, 2009

Introduction

Welcome to the first post of the Thrasher's Corner News Blog! I will strive to keep it interesting and informative so that you will be able to get some useful information out of it along the way. The main point of this forum is to inform people about our wonderful area and point out some real estate news and bulletins to help people who want to move here while I am at it.

This will be a learning experience for me as this is my first attempt at a blog. Back in the dark ages we actually published a newsletter for the Medical Dental Building in downtown Seattle and did the paste-ups of the stories by hand with real glue. The typesetting had to be done with special equipment and we would type up the stories (with a real typewriter) to give to the typesetter to do. It was quite archaic and I think we made about $0.18 an hour for our trouble. Hopefully, this will be a much easier process and will end up being a little more profitable.

Thanks for visiting. I hope you have a good experience and come back often.
Dennis