This is the latest from the Alderwood Water District about the on-going construction project in the Thrasher's Corner area.
d

North Creek North Segment Construction Update: (208th Street SE to 196th Street SE Snohomish County)

Frank Coluccio Construction (FCCC) will continue backfilling and restoring the micro-tunneling shafts located along 13th Drive SE.

FCCC construction crews will continue to work a standard 10 hour shift Monday thru Thursday. Friday’s will be reserved for low impact work and will only as necessary.

KLB construction crews are scheduled to work a standard 10 hour shift Monday thru Thursday. Friday and Saturday work is not currently scheduled (or expected) for this crew.

Last week a section of the existing sewer had to be removed and bypassed to get the shoring in, install the new pipe and remove the shoring. In the process of removing the shoring and restoring the existing pipe the side walls began caving. The contractor was slowed significantly due to the soils and safety issues. This unforeseen circumstance required extended hours for the contractor to safely control the excavation and secure the site.

Similar issues have occurred in the past along this portion of the project due to soil conditions, safety issues and other difficulties with the deep excavations and complexities associated with a very complex project.

These occurrences are very unfortunate and the District has appreciated your patience and understanding.
The District apologizes for the inconveniences and disruption to your daily routines.

KLB will be completing the installation of the last portion of open trench along 13th Drive SE. Open trench pipe installation is scheduled to be completed this week. Thank you again for your patience! The pipe installation will be followed by trench pavement repair and cleanup.

KLB has completed the open trench pipe work along 196th Street SE east of SR-527 (Bothell-Everett Highway). This final asphalt pavement overlay is scheduled for this week.

General cleanup by both FCCC and KLB will be ongoing.

North Creek South Segment Construction Update: (228th Street SE to 208th Street SE City of Bothell)

FCCC will continue removing shaft shoring located at the Arden Property.

KLB will continue with general site cleanup and preparation for asphalt paving. Asphalt paving for the New Tower property is tentatively scheduled to happen this week followed by curbs and completion of the landscape restoration .

Asphalt paving for the Arden Property is yet to be scheduled.

General Information

For questions regarding road improvements in Snohomish County please contact Doug McCormick, Snohomish County Program Planning Supervisor at 425-388-6655 or dmccormick@snoco.org.

If your neighbors would like to be added to the email distribution list, please have them contact the email box NorthCreek@awwd.com and we will get them on our email distribution list. If you have any issues, please contact Jay Hueter of Jacobs Engineering at 425-241-1023 or at jay.hueter@jacobs.com. In addition, the District’s Construction Project Manager, Bob Hastings is available to answer your questions or meet with you as needed. Bob can be reached at 425-743-4605 or bhastings@awwd.com.


Bob Hastings
Construction Project Manager
Alderwood Water and Wastewater District
bhastings@awwd.com
Tel. 425-743-4605
Fax 425-742-4562

No comments:

Post a Comment